DATE: July 9, 1996
SUBJECT:
APPROVE THE 17th AMENDMENT FOR KAPLAN/McLAUGLIN/DIAZ
MERRITHEW MEMORIAL HOSPITAL REPLACEMENT PROJECT (WH580B)
SPECIFIC REQUEST(S)OR RECOMMENDATIONS)&BACKGROUND AND JUSTIFICATION
I . RECOMMENDATION
1 . APPROVE: the Seventeenth Amendment of the Consulting Services
Agreement with Kaplan/McLaughlin/Diaz, and AUTHORIZE the
County Administrator or his designee to execute the Amendment
2 . AUTHORIZE: the County Administrator or his designee to issue
written authorizations for extra work, provided that the
cumulative total extra cost for all such authorizations shall
not exceed $25, 000 . 00 .
II . FINANCIAL IMPACT
This Amendment increases the Architect' s Payment limit by up to
$25, 000 for services required to respond to changes . Funds in the
capital account established for the project are sufficient to
cover the $25, 000 encumbered by this Amendment from bond proceeds
specified to the project . The cost for two items will be
reimbursed by the contractor via the change order process in the
amount of $11, 460 .
CONTINUED ON ATTACHMENT: YES SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE (S):
ACTION OF BOARD ON 1996 APPROVED AS RECOMMENDED OTHER
VOTE OF SUPERVISORS
I HEREBY CERTIFY THAT THIS IS A TRUE
UNANIMOUS(ABSENT ) AND CORRECT COPY OF AN ACTION TAKEN
AYES: NOES: AND ENTERED ON THE MINUTES OF THE BOARD
ABSENT: E). Be�42AUTAIN: OF SUPERVISORS ON THE DATE SHOWN.
Auditor-Controller F& 0 9 1996
ATTESTED
Contact: GSD (Accounting) PHIL BATCHELOR,CLERK OF THE BOARD OF
cc: Health Services Department SUPERVISORS AND COUNTY ADMINISTRATOR
F. Puglisi
Consultant (Via CAO) `
BY ,DEPUTY
k e-loAPPROVE THE 17th AMENDMENT FOR KAPLAN/MCLAUGLIN/DIAZ
MERRITHEW MEMORIAL HOSPITAL REPLACEMENT PROJECT (WH580B)
III . BACKGROUND
This change represents four extra services . Two items, the elevator
manufacturer substitution and modifications to the floating floor slab,
were initiated by the contractor for its convenience . The cost of the
Architect' s time to review these two items was the contractor' s
responsibility. The County will recoup these costs with credit change
orders . Changes to a piece of radiology equipment was necessary due to
model changes which occurred between design and the time the equipment
was ordered. These changes required additional design services to check
such items as structural support and equipment placement in the room.
The security requirements for the psych wards became more complex than
initially anticipated when design began. As a result additional design
work was required.