TO: BOARD OF SUPERVISORS, AS THE GOVERNING BODY OF THE CONTRA COSTA
COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: September 12, 1995
SUBJECT: CONSTRUCTION CONTRACT FOR DRAINAGE AREA 40A, PROJECT NO. 7565-
6D8571-93; AUTHORIZATION TO COMPLETE THE PROJECT AND TO PURSUE
LEGAL REMEDIES
peci is equest(s)or ecommen a ions)&OaCkground&justification
I. Recommended Action:
DECLARE that V&M Construction/Backhoe, hereafter referred to as V&M, is in material breach and
default of its contract dated July 6, 1994 for construction of the Drainage Area 40A Storm Drain
Improvements project for each of the reasons set forth below, and TERMINATE and CANCEL
V&M's rights under the contract on those grounds.
CONFIRM the assessment of liquidated damages in the sum of$53,500.00.
AUTHORIZE the Chief Engineer to proceed in the most expeditious manner, pursuant to the Public
Contract Code, to correct defective work, complete the construction of the above described
project, and deduct the reasonable expenses thereof from any moneys due or that may become
due V&M under the contract.
AUTHORIZE the County Counsel to pursue appropriate legal remedies, including the filing and
prosecution of lawsuits against V&M, American Bonding Company, and other parties responsible
for the damages and expenses incurred by the District.
II. Financial Impact:
Funds to correct defective work and complete the project will be deducted from any m eys due
or that may become due V&M under the contract.
Continued on attachment: X yes SIGNATURE-,A
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: APPROVED AS RECOMMENDED OTHER
VOTP.OF SUPERVISORS
✓✓ UNANIMOUS (ABSENT
AYES: NOES:
ABSENT: �_ ABSTAIN:
Contact: Joseph P. Murphy, (510) 313-2321
Orig.Div.: PW(Constr)
cc: County Administrator
County Counsel
Auditor-Controller
Public Works Dept.
- Administration, P. McNamee I hereby certify that this is a bw and correct copy of
- Accounting, R. Gilchrist an action taken and entered on the minutes of the
- R. Bruno Board of supervla re on the ddte shown.
Flood Control District
- M. Kubicek ATTESTED: ^ ` ��g 9�
P. Harrington PHIL BAT ELOR,clerk of the
V&M of Supervisors and County Administrator
East Bay Surety
JPM\TR:tt . _ _ ,Deputy
g:\const\BO\DA40-12.t9
` DA40A C. ` 3
Board Date: September 12,1995
Page 2 of 2
III. Reasons for Recommendations and Background:
On June 21, 1994, the Board awarded the construction contract for the Drainage Area 40A
Storm Drain Improvements project, located in the Martinez area, to V&M. The contract
required completion within 65 working days from the starting date.
On July 20, 1994 a notice to proceed was issued with a starting date of August 1, 1994 and
a contract completion date of October 31, 1994. As a result of inclement weather and extra
work required of V&M, the completion date was later extended to December 21, 1994.
For an extended period of time, V&M has failed to supply sufficient materials and workers to
correct defective work and complete the project, and the completion of the work is currently
eight months behind schedule. No work has been completed during the past three months.
The failure of V&M to diligently complete the work per the contract specifications and by the
contract completion date has resulted in additional expenses and other damages being
sustained by the District. Pursuant to the contract documents, V&M is liable to the District for
$53,500.00 in liquidated damages (i.e., 107 calendar days x $500.00/calendar day =
$53,500.00) for the delay between December 21, 1994 (adjusted contract completion date)
and April 7, 1995 (date when V&M claims to have completed its work). These liquidated
damages have been withheld previously from the contract funds for this project.
V&M has been repeatedly notified orallyy and in writing of the lack of progress in completing
this project. Despite these notices, V&M has failed to complete the work. The latest notice
was sent to V&M and its bonding company by certified mail, return receipt requested, on
August 8, 1995 and was received by VMon August 14, 1995. The notice required V&M, no
later than ten days after receipt of the notice, by August 24, 1995, to correct certain defective
work and return to the job with sufficient materials and workers to complete the job, and
warned V&M that, if these things were not done by the deadline, the District would terminate
V&M's rights under the contract and complete the work with other forces and deduct the
reasonable expenses thereof from the contract funds. V&M failed to meet the deadline and
has continued in its failure to supply sufficient materials and workers to complete the work.
On August 23, 1995, the District was notified in writing by V&M that V&M would not complete
the remaining contract work.
It is recommended that the Board terminate and cancel V&M's rights under the construction
r contract for each of the deficiencies listed above; confirm the assessment of liquidated
damages; direct that the Chief Engineer proceed with the completion of the project, enter into
any necessary contracts in accordance with the Public Contract Code and deduct the amount
thereof to complete the work from any moneys due or that may become due V&M under the
contract; and authorize the County Counsel to pursue appropriate legal action, including the
filing and prosecution of lawsuits against V&M, its bonding company and other responsible
parties.
IV. Consequences of Negative Action:
The defective work and unfinished construction will remain an impediment to the assumption
of maintenance responsibilities of the storm drain facilities and improvements by the County
and the City of Martinez.