HomeMy WebLinkAboutMINUTES - 09131994 - 1.18 TO: BOARD OF SUPERVISORS FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR DATE: September 13, 1994 SUBJECT: Approval of Project Contingency Fund increase and Contract Change Order No. 4 for the Avon Bridge Rehabilitation and Seismic Retrofit project, Project No. 0662-6R4089-90, Avon area. Specific Request(s) or Recomrnendation(srX Backgroundu i ica ion I. Recommended Action: APPROVE Project Contingency Fund increase of$1,300.00 and Contract Change Order No. 4 in the approximate amount of$2,300.00 and AUTHORIZE the Public Works Director to execute it in order to compensate the contractor, Valentine Corporation, for additional work due to modifications to the swing bridge. II. Financiallmpact: The source of funds is Federal Funds (81%), Matching State Funds (1%), and Road Funds (18%). III. Reasons for Recommendations and Background: Unforeseen extra work not on the original plan was required to operate the bridge swing span. Because the total of Contract Change Orders Nos. 14 exceeds $25,000.00 and exceeds the Project Contingency Fund, Board approval of the Change Order and the increase in the Project Contingency Fund is required. IV. Consequences of Negative Action: Without approval, the contractor will not receive payment for work required. Continued attachment: _yes SIGNATURE: RECOMMENDATION OF COUNTY ADMINISTRATO RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON:-.SFP 13 199 —APPROVED AS RECOMMENDED X OTHER VOTE OF SUPERVISORS UNANIMOUS (ABSENT_) S: NOES: ABSENT: ABSTAIN: Contact: Joseph P. Murphy, (510) 313-2321 Orig. Div.: PW(Constr) cc: County Administrator Auditor-Controller Public Works Design Accounting, R.Gilchrist R. Bruno - Contractor aneactiio, taken eantterred on the minutes of the ATTESBoard TED, 07 C.8 1 c3 199}town. DG\tt PHIL BATCHELOR,clerk of the Board c:BOWBR-13.t9 of supervisors and County Administrator By .Deputy