HomeMy WebLinkAboutMINUTES - 08091994 - 1.5 (2) N File: 250-9366/B. 4 .4 1'S0
THE BOARD OF SUPERVISORS
CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on August 9, 1994, by the following vote:
AYES: Supervisors Smith, Bishop, DeSaulnier, Torlakson and Powers
NOES: None
ABSENT: NOne
SUBJECT: Award of Contract for Emergency Generator and Back-up
Air Conditioner for Data Processing at 595 Center
Avenue, Martinez, for Health Services Department
Budget Line Item No. 6971-4569
Authorization No. 0927-WH569B
( formerly WPE226 )
Bidder Total Amount Bond Amounts
Alhambra Electric $113,500 . 00 Payment:
836 Alhambra Avenue Base Bid Only $ 56 ,750 . 00
Martinez, CA 94553 Performance:
$113,500 . 00
Howell & Clark, Inc.
dba Empire Electric Construction Co.
San Francisco, California
P. M. & M. Electric, Inc.
Martinez, California
Westmac Builders
Oakland, California
Abbett Electric Corporation
San Francisco, California
Marvin Busby Company, Inc.
Oakland, California
The above-captioned project and the specifications therefor
having been previously approved, Addendum No. 1 having been issued
and approved, and bids having been duly invited and received by the
Director of General Services on July 14 , 1994 ; and
The Contract Compliance Officer having determined that the
lowest monetary bidder, Howell & Clark, Inc. dba Empire Electric
Construction Co. ( "Empire" ) has failed to meet the MBE and WBE
goals for this project (i .e. , 14% and 6% respectively) and has
failed to document an adequate good faith effort to comply with
said goals and the requirements of the County' s Minority and Women
Business Enterprise Program, as required by the project
specifications, and the Contract Compliance Officer recommending
rejection of said bid; and
Empire having been notified in writing of the Contract
Compliance Officer' s determination and not having appealed it, as
required by the project specifications; and
The bidder listed first above, Alhambra Electric,
( "Alhambra" ) , having submitted the lowest responsive and
responsible bid; and
The Contract Compliance Officer having reported that
Alhambra has attained MBE participation of 16 . 3% and WBE
participation of 16 . 3%, which exceeds the MBE and WBE goals for
this project and complies fully with the requirements of County' s
Minority and Women Business Enterprise Program; and
Page 1 of 3