SUBJECT: APPROVAL OF FINAL AND BALANCING CONTRACT CHANGE ORDER NO. 3 FOR AIP 3-06-
0050-05 AT BUCHANAN FIELD AIRPORT
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) &BACKGROUND AND JUSTIFICATION
I. Recommended Action:
AUTHORIZE the Public Works Director to execute the Final and Balancing Contract Change Order
No. 3 to compensate the Contractor, Vintage Grading and Paving, Inc., for additional work at
Buchanan Field Airport.
Il. Financial Impact:
This Change Order requires an adjustment of $85,713.86 to the Contract price to date of
$653,892.40 resulting in,a Contract price of $739,606.26.
III. Reasons for Recommendations and Background:
The Change Order deals.with reconstruction and overlay of the east ramp aircraft parking area and
the patching and seal coat of hangar taxilanes at Buchanan Field Airport.
Continued on Attachment: SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON AUG 1 T i993 APPROVED AS RECOMMENDED OTHER
VOTE OF SUPERVISORS
V UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN: I hereby certify that this to a true and correct copy 71
an action taken and entered on the minutes of tba
HEW:rs Board of Supervnq�,ontthtdalashown.
c:\17v.t8 ATTESTED: pP�1�UJ1�7 1� yyyy�J
PHIL BATCHELOR,Clerk of the Board
Orig Div: Airports - Contact H. Wight 646-5722 of Supervisors and County Administrator
cc: County Administrator gj
Ayd �• ��,
Public Works Director By ,t Y /Y "Deputy
Public Works Accounting
Auditor/Controller
Aviation Advisory Committee
Federal Aviation Administration
Vintage Grading & Paving, Inc.