HomeMy WebLinkAboutMINUTES - 09221992 - 1.1 TO: BOARD OF SUPERVISORS FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR DATE: September 22, 1992 SUBJECT: APPROVAL of Contract Change Order 4 for the Highway 4 Widening project in the Oakley area, Project No. 4660-6X4014-89 Specific Request(s)or Recommendation(s)&Background&Justificatilon I. Recommended Action: APPROVE Contract Change Order No. 4 in the approximate amount of $5,500.00 and AUTHORIZE the Public Works Director to execute it in order to compensate the contractor, McDonald Construction Co., for additional work required by CALTRANS. II. Financial Impact: The project contingency funds are sufficient to cover the change order costs. This project is funded by the Redevelopment Agency (60%), Oakley Area of Benefit (26%) and Developer Contribution (14%). I III. Reasons for Recommendations and Background: The total of contract change orders nos. 1 through 4 exceeds $25,000.00, requiring Board approval. IV. Consequences of Negative Action: The lack of approval would preclude payment for work required to complete the project. Continued on attachment: _yes SIGNATURER. c �� RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON: SEP 2+ 21992 APPROVED AS RECOMMENDED OTHER VOTE OF SUPERVISORS UNANIMOUS (ABSENT-J AYES: NOES: ABSENT: ABSTAIN: Contact: B.J. Kerekes, (510) 313-2321 Orig. Div.: PW(Constr) cc: County Administrator Auditor-Controller Public Works I hereby certify that this is a true and correct copy - Design an action taken and entered on the minutes of the - Accounting, R. Gilchrist Board of Supervisors on the date sshQoQwn. - R. Bruno ATTESTED: - SEP� .2 Contractor PHIL BATCHELOR,Cierk of the Bcard of Supervisors and County Administrator By - ... _-,Deputy GB\tt c:BO\H4BB-22.t9