TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: September 15, 1992
SUBJECT: Approving Oakley Road Reconstruction Project, Oakley Area.
Project No. 0662-6134152-91, CP # 92-59.
Specific Request(s) or Recommendations) & Background & Justification
I. RECOMMENDED ACTION:
APPROVE Project, and
FIND, on the basis of the initial study and all comments received, that there is no substantial evidence
that the project will have a significant effect on the environment,
ADOPT the Negative Declaration in compliance with the California Environmental Quality Act, and
DIRECT the Public Works Director to begin right of way acquisition and to prepare contract plans and
specifications for construction.
DIRECT the Director of Community Development to file a Notice of Determination and a Certificate of
Fee Exemption: De Minimis Impact Finding with the County Clerk.
DIRECT the Public Works Director to arrange for payment of the $25.00 handling fee to the County
Clerk.
II. FINANCIAL IMPACT:
The estimated project cost is $425,000.00, funded by State Transportation Partnership Program (24%)
Developer Contributions (28%) and Oakley/North Brentwood Area of Benefit (48%).
Continued on Attachment: X SIGNATURE:
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON /?F.APPROVED AS RECOMMENDED_�OTHER_
VOTE OF SUPERVISORS
T� UNANIMOUS (ABSENT
AYES: NOES:
ABSENT: ABSTAIN:
ES:jlg
c\BO:bol5.tg
Orig. Div: Public Works (Design Division)
Contact: Elmer Schaal,313-2234 1 hereby certify that this Is a true And correct copy of
CV. County Administrator an action taken and entered on the minutes of th3
Attn: E. Kuevor Board of Supe ors o th ate shown.5-1
/ p 7
Auditor-Controller ATTESTED: 5 /..�2ig-
PW Accounting
Construction PHIL BH7 HELOR,Clerk of the Board
of Supervisors and County Administrator
Community Development
By Deputv
I
Approving Oakley Road Reconstruction Project, Oakley Area
September 15, 1992
Page 2
III. REASONS FOR RECOMMENDATION/BACKGROUND:
The project includes reconstructing Oakley Road to a new vertical and horizontal alignment from Live
Oak Road to Empire Avenue.
It is needed to improve the safety of the road and to set the alignment for future development.
A Negative Declaration of environmental significance pertaining to this project was published on August
18, 1992 with no protest, and the Board has considered the negative declaration together with all
comments received during the public review period,
This project has been found tobe de minimis.in its effect on the environment,_and is exempt from the
$1,250.00 Fish and Game fling fee.
IV. CONSEQUENCES OF NEGATIVE ACTION:
Delay in approving the project will result in a delay of design and construction and may jeopardize