HomeMy WebLinkAboutMINUTES - 07211992 - 1.19 TO: BOARD OF SUPERVISORS AS THE GOVERNING BODY OF THE CONTRA COSTA
COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: July 21, 1992
SUBJECT: Authorize the Issuance of Purchase Orders to East Bay Municipal Utility District and
Pacific Gas and Electric Company for Utility Relocations for the Drainage Area 10, Lines
C-2, C Extension and A-1 Project in the Town of Danville
Project No.: 7554-6D8464-91
Specific Request(s)or Recommendation(a)i Background ik Justification
I. Recommended.Action:
AUTHORIZE the issuance of purchase orders in the amount of $25,000 each to East Bay
Municipal Utility District (EBMUD) and Pacific Gas and Electric Company (PG&E) for relocation
of their facilities in conjunction with the Drainage Area 10, Lines C-2, C Extension and A-1
Project.
II. Financial.Impact:
The estimated cost of the utility relocations is$25,000 for EBMUD and $25,000 for PG&E,funded
by Drainage Area 1,0 (100%).
III. Reasons for. Recommendations and Background:
The Drainage Area 10;1project improves drainage on Prospect Avenue, EI Dorado Avenue and
Verona Avenue in the Town of Danville. The project was designed to minimize utility conflicts.
However,. conflicts with EBMUD and PG&E facilities could not be entirely avoided and utility
relocations are necessary. The utility companies will be reimbursed for the actual cost of the
relocations on a time and materials basis.
IV. Consequences of Negative Action:
If the purchase orders are not issued, the utilities will not be relocated and the drainage lines
cannot be installed.
Continued on Attachment:_ SIGNATURE:
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON JUL 2 11992, APPROVED AS RECOMMENDED OTHER
VOT5,OF SUPERVISORS
1/ UNANIMOUS (ABSENT
AYES: NOES:
ABSENT: ABSTAIN:
JRB:jlg I hereby certify that this Is a true and correct copy Y
c\BO:bo21.t7 an action taken and entered on the minutes of the
Orig. Div: Public Works(Design Division) Board of Supervisors on the date shown.
cc: County Administer ATTESTED: --4.U�2 c
Auditor-Controller PHIL BATCHELOR,Clerk o he Board
PW Accounting of Supervisors and unty Administrator
Flood Control District
Construction
ev ,Ceputy