HomeMy WebLinkAboutMINUTES - 09171991 - 1.1 (2) TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: September 17, 1991
SUBJECT: Accept Federal Aviation Administration (FAA) Grant for$861,731.00 (AIP Project No. 3-06-
0050-07) for Buchanan Field Airport Improvements
SPECIFIC REQUESI'(S)OR REQOMIME.NDAIION(S)&BACKGROUND AND JUSTIFICATION
I. Recommended Action:
APPROVE and AUTHORIZE the Chairman of the Board of Supervisor to sign a Statement of
Acceptance of said Grant Offer (entitled part II Acceptance) on behalf of Contra Costa County;
and
AUTHORIZE and DIRECT the Clerk of the Board to attest the signature of the chairman and to
impress the official seal of Contra Costa County on the aforesaid Statement of Acceptance; and
AUTHORIZE and DIRECT County Counsel to sign a certificate of Sponsors Attorney (entitled
CERTIFICATE OF SPONSORS ATTORNElr7 which certifies that the acceptance complies with
all applicable laws and constitutes a legal and binding obligation.
II. Financial Impact:
The total cost of the project is $957,479. Ten percent (10%) of the project in the amount of
$95,748 is the responsibility of Contra Costa County and will be paid out of the Airport
Enterprise Fund utilizing enterprise funds or a loan from the State of California Department of
Transportation (CALTRANS) matching loan program.
III. Reasons for Recommendations and Background:
On February 27, 1990 the Board of Supervisors authorized a preapplication in the amount of
$509,215. This preapplication was amended March 20, 1990 and again amended May 21, 1991.
These amendments bring the total cost of the project to $957,479.
Continued on Attachment: x SIGNATURE: iG� GP
_RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON SEP 17 1991 APPROVED AS RECOMMENDED V OTHER
VOTE OF SUPERVISORS
UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN: I hereby certify that this Is a true and correct copy of
an action taken and entered on the minutes of the
HEW:sh Board of Supervisors
onthedate town.
bo17.t9 ATTESTED: ( 11 1
Orig Div:Airports PHIL BATCHELOR,Clerk of the Board
cc: County Administrator of Supervisors and County Administrator
GMEDA Director Qn ,,Q
Public Works Director By ° dALd,44 "'-`�'� �Deputy
Public Works Accounting
Auditor/Controller
Aviation Advisory Committee
Federal Aviation Administration
Accept FAA Grant
September 17, 1991
Page 2
The work under this project includes installation of the noise monitoring system, construction of taxiway
and landing area for the future helicopter and emergency operating areas, some lighting marking and
fencing and some storm drainage work.
It is anticipated that the noise monitoring system will be installed by the end of 1991. Most of the rest of
the work will be done during the summer of 1992.