HomeMy WebLinkAboutMINUTES - 08061991 - 1.6 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: August 6, 1991
SUBJECT: Approval of Contract Change Orders Nos. 9, 10 and 11 for the Highway 4 Widening
Project in the Discovery Bay Area.
Project No. 4660-6X4122-88
Specific Request(s)or Recommendation(s)&Background&Justification
I. Recommended Action:
Authorize the Public Works Director to execute Contract Change Orders Nos. 9, 10 and 11, in the
approximate amounts of $14,000.00, $6,000.00 and $7,000.00 respectively to compensate the
contractor,Teichert Construction Co.,for modifying existing improvements to fit the new roadway,
installing drainage pipe, grinding the bridge decks, and to correct flooding problems.
II. Financial Impact:
The project contingency funds are sufficient to cover the change order costs. The source of
funds is the Discovery Bay Area of Benefit.
III. Reasons for Recommendations and Background:
The cumulative total of Contract Change Orders No. 1 thru No. 11 exceeds $25,000.00, requiring
approval. The existing roadway and facilities had to be modified, paving was impossible due to
flooding, and existing facilities had to be modified.
IV. Consequences of Negative Action:
The lack of approval would preclude payment for work required.
Continued on attachment: _yes SIGNATURE:/2% lir
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: AUG 6 1991 APPROVED AS RECOMMENDED ✓ OTHER
VOTE OF SUPERVISORS
_V/' UNANIMOUS (ABSENT
AYES: NOES:
ABSENT: ABSTAIN:
Orig. Div.: PW(Constr)
cc: County Administrator
Auditor-Controller I hereby certify tnet this Is a true and correct copy of
n ac
Public Works ation taken and entered on the minutes of the
Board of Supervisors on the date shown.
- Design ATTESTED: AUG F 1991
- Accounting, R. Gilchrist PHIL BATCHELOR,Clerk of the Board
- R. Bruno of Supervisors andCo my Administrator
Contractor
DG\dp\tt
BygAi ,Deputy
c:BO\H4WD-6.t8