SPECIFIC REQUEST(S) OR RECOMMENDATIONS(S) & BACKGROUND AND JUSTIFICATION
RECOMMENDATIONS
Approve contract amendment with Onmi Means for Additional Traffic
Mitigation Study at the Pleasant Hill BART Station and authorize
the Executive Director or his designee to execute said contract
amendment.
FISCAL IMPACT
Redevelopment Agency tax increments will cover the .additional
$5040. 00 cost of this contract amendment.
BACKGROUNDIREASONS FOR RECOMMENDATIONS
On September 26, 1989 the Contra Costa County Redevelopment Agency
acting on the recommendation of the Pleasant Hill BART Steering,
Committee, entered into a contract with Omni Means, an Engineering
Consulting Firm to complete an Additional Traffic Mitigation Study
in the Pleasant Hill BART Station Area. The consultant has
completed the work. Additional work beyond that contemplated in
the initial scope of work was required. This additional work
warrants an increase in the payment limit for said contract in the
amount of $5, 040. 00.
CONTINUED ON ATTACHMENT: YES SIGNATURE:
RECOMMENDATION OF EXECUTIVE DIRECTOR RECOMMENDATION GENCY` COMMITT
APPROVE OTHER
SIGNATURE(S) :
ACTION OF AGENCY ON August 7, 1990 APPROVED AS RECOMMENDED X OTHER
VOTE OF COMMISSIONERS
X I HEREBY CERTIFY THAT THIS IS A
_ UNANIMOUS (ABSENT ) TRUE AND CORRECT COPY OF AN
AYES: NOES: ACTION TAKEN AND ENTERED ON THE
ABSENT: ABSTAIN: MINUTES OF THE REDEVELOPMENT
AGENCY ON THE DATE SHOWN.
cc: Redevelopment Director ATTESTED August 7, 1990
CAO PHIL BATCHELOR,
Auditor-Controller AGENCY SECRETARY
County Counsel
BY `� , DEPUTY