TO: BOARD OF SUPERVISORS, AS THE GOVERNING BODY OF THE CONTRA COSTA
COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: August 7, 1990
SUBJECT: DRAINAGE AREA 52C JOINT EXERCISE OF POWERS AGREEMENT
Project No.: 7571-6D8510
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) &BACKGROUND AND JUSTIFICATION
I. Recommended Action:
Approve and authorize the Chair, Board of Supervisors, to execute the Joint Exercise of Powers
Agreement with the City of Brentwood for the construction of a portion of Line A in Drainage
Area 52C.
II. FinancialImpact:
The construction of Line A will cost approximately $332,000. This project will be financed as
follows:
Drainage Area 52C $282,000
Loan from City to Drainage Area 52C 50,000
III. Reasons for Recommendations and Background:
The City of Brentwood has designed, and is constructing an expansion project to their
wastewater treatment facility. As a part of the expansion project, the City is required to relocate
an existing 14-inch diameter irrigation drain line which currently drains the areas around the plant
site.
Continued on Attachment: X SIGNATURE:
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON AUG 7 1990 APPROVED AS RECOMMENDED OTHER _
VOTE OF SUPERVISORS
UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN:
SK:dmw
c:BO\DA52cJEPA.BO
Orig. Div: Public Works (FCE)
cc: County Administrator I hereby certify that this is a rnw and correct Copy of
Community Development an action taken ano entered on the minutes of the
County Auditor- Controller Board of Supervisors on the date shown.ty
County Counsel ATTESTED: AUG [ iqqn
P.W. Accounting PHIL BATCHELOR,clerk of the Board
Flood Control Engineering all Supervisors and county Administrator
/-2z
Board of Supervisors
Drainage Area 52C JEPA
August 7, 1990
Page 2
III. Reasons for Recommendations and Background: (Continued)
The proposed location of the 14-inch line is in close proximity to a proposed Flood Control
District 30-inch diameter drainage line (Line A). The proposed 30 inch line is designed to serve
as an outfall line from four detention basins to Marsh Creek, in Drainage Area 52C.
In order to avoid the extra expense and disruption that separate construction of the 14-inch and
30-inch lines would entail, the City of Brentwood and the Flood Control District desire to install
Line A as a part of the City's expansion project. The purpose of this agreement is to provide
for the apportionment of project duties and costs between the City and Flood Control District.