TO: BOARD OF SUPERVISORS,AS GOVERNING BOARD OF CONTRA COSTA COUNTY
FLOOD CONTROL & WATER CONSERVATION DISTRICT
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: AUGUST 14, 1990
SUBJECT: WILDCAT-SAN PABLO CREEKS CORPS OF ENGINEERS PROJECT
SPECIFIC REQUEST(S)OR RECOMMENDATIONS)&BACKGROUND AND JUSTIFICATION
I. Recommended Action:
1. AUTHORIZE staff to notify the Corps of Engineers that the Flood Control District requests
a temporary suspension of work on Contracts #3 and #4 until State Subvention funding
is reestablished.
2. APPROVE the termination of all rights of way and relocation work being performed by
staff for implementation of Contracts #3 and #4.
3. DIRECT the Chief Engineer to prepare a letter for the Chairs' signature explaining to our
local State Legislators the consequences of the States' failure to provide Flood Control
Project Subvention funding and requesting their support for a State Bond Issue to fund
the program for two years.
II. Financial Impact:
Delay of the above projects for one or more years will increase the final project costs by
approximately$250,000 per year. Flood Control Zones 7 and 3B and Drainage Area 73 will also
collectively experience a $200,000 to $250,000 financial loss due to the States' failure to pay
subvention claim until FY 1991-92.
Continued on Attachment: X SIGNATURE:
_ RECOMMENDATION OF COUNTY ADMINISTRATOR _ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON AUG 14 1990 APPROVED AS RECOMMENDED V*� OTHER
VOTE OF SUPERVISORS
JC UNANIMOUS (ABSENT 1
AYES: NOES:
ABSENT: ABSTAIN:
1 hereby certify that this is a Crus and correct copy of
an action taken and entered on the minutes of the
MFK:Iv Board of Supervisors on the date shown.
a:bo/14.t8 ATTESTED: AUG 11 1990
PHIL BATCHELOR,Clerk of the Board
Orig. DIV: Public Works (AD) of Supervisors and CountivAAdminlstrator
cc: SEE PAGE TWO hQ.,t 1.t►�a Deputy
Wildcat-San Pablo Creeks
August 14, 1990
Page Two
III. Reasons for Recommendations and Background:
Flood Control Zone 7 and Drainage Area 73 have insufficient capital to proceed further with the
Wildcat-San Pablo Creek improvements without the 70 percent State Subvention participation.
Both entities have already been financially over extended to absorb all the project changes
required by the Design Team Plan.
Contract #3 is for the Wildcat Creek improvements from Southern Pacific Railroad right of way
to a point downstream of Rumrill Road. Contract #4 is for the San Pablo Creek improvements
from Southern Pacific Railroad right of way upstream to Giant Highway
IV. Consequences of Negative Action:
Failure to stop the work now will result in additional local project costs for which funds are not
available.
cc: County Administrator
County Counsel
Community Development
Auditor-Controller