TO: BOARD OF SUPERVISORS, AS THE GOVERNING BODY OF CONTRA
COSTA COUNTY FLOOD CONTROL AND WATER CONSERVATION
DISTRICT
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: SEPTEMBER 27, 1988,
SUBJECT: AUTHORIZE ACCEPTANCE OF IN LIEU OF CONSTRUCTION CASH
PAYMENTS FROM DEVELOPERS REQUIRED TO MITIGATE STORM
WATER RUNOFF IN THE SAN RAMON WATERSHED, FLOOD CONTROL
ZONE 3B
Specific Request(s) or Recommendation(s) & Background &
Justification
I. RECOMMENDATION
AUTHORIZE the Chief Engineer to accept in lieu of construction
cash payments from developers required by their conditions of
approval to mitigate the accumulation hydrologic impact from
their development on the San Ramon Creek drainage system.
II. FINANCIAL IMPACT
By combining numerous small projects into one large project
constructed annually, both the District and the developers will
save on project administration costs.
III. REASONS FOR RECOMMENDATION/BACKGROUND
The developers in the San Ramon Watershed are being required to
meet a minimum mitigation standard where their developments
increase the amount of impervious surface. The mitigation
standard is to excavate one cubic yard of material from San Ramon
Creek for each fifty square feet of new impervious surface. On
small developments the mitigation work can be accomplished in one
or two days work.
Continued on attachment: X yes Signature:
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Signature(s)
Action of Board on: SEP 271988
Approved as Recommended_ Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS
A TRUE AND CORRECT COPY OF AN
Unanimous (Absent ) ACTION TAKEN AND ENTERED ON
Ayes: Noes: THE MINUTES OF THE BOARD OF
Absent: Abstain: SUPERVISORS ON DATE SHOWN.
Attested SEP 2 7 198$.
PHIL BATCHELOR,
CLERK OF THE BOARD
OF SUPERVISORS AND
COUNTY ADMINISTRATOR
/ s
By 66
Distribution: DEPUTY CLERK
See Attachment
The District has received letters from the Smith Companies,
Retail Property Development, Co. and Mr. Thomas J. Heafey
requesting they be allowed to make a cash payment for the value
of the work in lieu of performing the work.
It is recommended that the Chief Engineer be authorized to accept
these in lieu payments, to combine them with other future
payments and to annually prepare a single contract to implement
the required mitigation work.
IV. CONSEQUENCES OF NEGATIVE ACTION
The District and developers would continue to incur higher
administrative costs in implementing the required mitigation
work.
MFK:md
27 .t9
Orig. Div. :Public Works (FCE)
cc: County Administrator
Community Development
Building Inspection
County Counsel
County Assessor
County Treasurer - Tax Collector
County Auditor - Controller
Smith Companies via Public Works
Retail Property Development Co. via Public Works
Mr. Thomas J. Heafey, via Public Works