HomeMy WebLinkAboutMINUTES - 09261989 - 1.4 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: September 26, 1989
SUBJECT: Approve and Authorize the Public Works Director to.
execute The Consulting Services Agreement for Phase I
Preliminary Engineering for State Route 4/Bailey Road
Interchange. (Project: 0357-6X4155)
Specific Request(s) or Recommendation(s) & Background &
Justification
I. RECOMMENDATION
Approve and authorize the Public Works Director to execute the
Consulting Services Agreement with John Carollo Engineers to
perform phase I preliminary engineering for State Route 4/Bailey
Road Interchange project.
II. FINANCIAL IMPACT
Funding for this agreement will come from funds advanced from
the Bay Area Rapid Transit District (BARTD) for project
development of State Route 4 over the Willow Pass Grade. No
County funds will be required.
Continued; on attachment: yes Signatur
i
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Signature(s)
Action of Board on: SEP 2 6 1989
Approved as Recommended_ Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS
A TRUE AND CORRECT COPY OF AN
Unanimous (Absent X ) ACTION TAKEN AND ENTERED ON
Ayes: Noes: THE MINUTES OF THE BOARD OF
Absent: Abstain: SUPERVISORS ON DATE SHOWN.
Attested SEP 2 6 1989
Orig. Div. :Public Works (RE) PHIL BATCHELOR,
cc: R. Snyder, BARTD CLERK OF THE BOARD
R. Anderson, Caltrans OF SUPERVISORS AND
R. Zapf, Pittsburg COUNTY ADMINISTRATOR
R. deVincenzi, CCD
R. MC Cleary, CCTA
M. Harrington, JCE
R. Gilchrist, PW Accounting
RVF:md
BO: 26a.t9
BY
DEPUTY CLERK
September 26, 1989
Page Two
III. REASONS FOR RECOMMENDATION/BACKGROUND
With the passage of Measure C in November 1988, funding for State
Route 4 improvements and the BART extension to East County became
a reality. BARTD is scheduled to have their east county
extension ' to Bailey Road completed by 1997 . BART is to be
located within the median at Bailey Road, so all interchange
improvements have to be completed by December 1994 . To meet this
schedule, phase I preliminary engineering has to start
immediately.
The preliminary engineering is separated into two phases to
expedite the project. Phase I preliminary engineering will allow
for the completion of the Project Study Report (PSR) , a report
required so that the project may be included in the 1990 State
Transportation Improvement Program (STIP) . Once the project is
in the STIP, Caltrans can allocate staff time and resources
toward the project. Phase I work will be done prior to approval
of a cooperative funding agreement with the Contra Costa
Transportation Authority (CCTA) .
After an extensive consultant selection process, John Carollo
Engineers has been selected to prepare the PSR. As soon as the
cooperative agreement with CCTA is executed, we contemplate
amending the consulting services agreement to include the
environmental documentation.
Phase II preliminary engineering will include preparation of the
plans, specifications, and cost estimate for the project.
Consultant selection for phase II engineering will begin near the
completion of the project report.
IV. CONSEQUENCES OF NEGATIVE ACTION
If this agreement is not approved, the project completion date
will be extended which will affect the completion date for the
BARTD' s east county extension.