HomeMy WebLinkAboutMINUTES - 09261989 - 1.3 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: September 26, 1989
SUBJECT: Nichols Road Overhead Replacement Project
Project No. : 0662-6R4136 Task: ACQ Account: . 3540
SPECIFIC REQUEST(S) OR RECOMMENDATIONS) 8 BACKGROUND AND JUSTIFICATION
I. Recommended Action:
A. APPROVE Right of Way Contract and ACCEPT Grant of
Temporary Easement from Allied-Signal Inc. , dated August
22, 1989.
B. AUTHORIZE Public Works Director to execute said Right of
Way Contract on behalf of the County.
C. 'APPROVE payment of $1,500. 00 for said property rights
and AUTHORIZE the Auditor-Controller to issue a check in
-said amount payable to Allied-Signal Inc. , to be
forwarded to the Real Property Division for delivery.
D. DIRECT the Real Property Division to have the above
referenced Grant of Temporary Easement recorded in the
office of the County Recorder.
II. Financial Impact:
Funding of the $1,500 is 80% reimbursable from the Federal
Highway Administration and 20% reimbursable from local
sources.
III. Reasons for Recommendations/Background:
These property rights are required for the Nichols Road
Overhead Replacement project in accordance with approved
plans and specifications.
IV. Consequences of Negative Action:
The project will not have sufficient land rights to allow
construction in accordance with the approved plans and
specifications.
CONTINUED ON ATTACHMENT: YES SIGNATURE: 4&�
(�
APPROVE OTHER
SIGNATURES) /�
ACTION OF BOARD ON SEP 2 9 1q
989 APPROVED AS RECOMMENDED � OTHER
VOTE OF SUPERVISORS
UNANIMOUS (ABSENT ) I HEREBY CERTIFY THAT THIS IS A TRUE
AYES: NOES: AND CORRECT COPY OF AN ACTION TAKEN
ABSENT: ABSTAIN: AND ENTERED ON THE MINUTES OF THE BOARD
OF SUPERVISORS ON THE DATE SHOWN.
ATTESTED SEP 2 6 1989
PHIL BATCHELOR, Clerk of the Board of
Supervis1nd,,,County Administrator
BYDEPUTY
DD:Lo
B0:2.t9
Orig. Div: Public Works (R/P)
cc: County Administrator
Auditor-Controller (via R/P)
P. W,. Accounting
Recorder (via R/P)