HomeMy WebLinkAboutMINUTES - 08081989 - 1.8 TO: BOARD OF SUPERVISORS, as the Governing Body of the Contra Costa County Flood Control and Water Conservation District FROM: J. MICHAEL WALFORD, CHIEF ENGINEER DATE: AUGUST 8, 1989 SUBJECT: SAN RAMON CREEK BYPASS, PHASE III Project No. : 7520-6B8636 Task: ACQ Account: 3540 SPECIFIC REQUEST(S) OR RECOMMENDATIONS) & BACKGROUND AND JUSTIFICATION I. Recommended Action: A. APPROVE Right of Way Contract and ACCEPT Grant Deed dated July 23, 1989, from David E. McClun and Diana McClun. B. AUTHORIZE Chief Engineer to execute said Right of Way Contract on behalf of the District. C. APPROVE payment of $12 ,500 for said property rights and AUTHORIZE the Auditor-Controller to issue a check in said amount payable to First American Title Guaranty Company, Escrow No. 711701 to be forwarded to the Real Property Division for delivery. D. DIRECT the Real Property Division to have the above referenced Grant Deed recorded in the office of the County Recorder. Cont'd on Attachment: X yes Signature: � � Recommendation of County Administrator _ Recommendation of Board Committee Approve Other Signatures) Action of Board on AUU Approved as recommended X _ Other Vote of Supervisors Unanimous (Absent ) I HEREBY CERTIFY THAT THIS Ayes: Noes: IS A TRUE AND CORRECT COPY Absent: Abstain: OF AN ACTION TAKEN AND ENTERED ON THE MINUTES OF THE BOARD OF SUPERVISORS ON DATE SHOWN. ATTESTED AUG 8 1989 PHIL BATCHELOR, Clerk of the Board of Supervisors and County Administrator NW:rs BY ffAAA ,C1taA6 BO: 128.t8 DEPUTY Orig. Div: Public Works (R/P) cc: County Administrator Auditor-Controller (via R/P) P. W. Accounting Recorder (via R/P) /-00 II. Financial Impact: Payment of $12, 500 from Flood Control Zone 3B funds which are 100% reimbursable from State Department of Water Resources. III. Reasons for Recommendations and Background: These property rights are required for the San Ramon Creek Bypass project in accordance with approved plans and specif- ications. IV. Consequences of Negative Action: The project will not have sufficient land rights to allow construction in accordance with the approved plans and specifications.