HomeMy WebLinkAboutMINUTES - 09131988 - 1.4 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: September 13 , 1988
SUBJECT: Highway 4 at Willow Pass Grade
Project No. =4,66x-6X4171-88
Specific Request(s) or Recommendation(s) & Background &
Justification
RECOMMENDED ACTION:
APPROVE the consulting services agreement with Centennial Civil
Engineers, Inc, for construction engineering services for the
Highway 4 Widening at Willow Pass Grade Project and AUTHORIZE the
Public Works Director to execute the agreement.
FINANCIAL IMPACT:
The maximum contract cost which is not to be exceeded without
written approval by the Public Works Director is $160, 000. 00. It
is funded by the Joint Powers Authority (100%) .
REASONS FOR RECOMMENDATION/BACKGROUND:
The County has entered into a cooperative agreement with the State
of California for improvements to State Highway Route 4 including
adding one west-bound lane over the Willow Pass Grade.
The services of a consultant are required to provide adequate
construction engineering staff services.
CONSEQUENCES OF NEGATIVE ACTION:
If construction engineering staff services are not provided by
consultant, staff would have to be provided by the Public Works
Department thus hindering the progress of other projects.
Continued on attachment: yes Signature, -
A
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Signature(s) :
Action of Board on: SLF 13 1988
Approved as Recommended_ Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
_)!�._Unanimous(Absent ) AND ENTERED ON THE MINUTES OF THE
Ayes: Noes: BOARD OF SUPERVISORS ON DATE SHOWN.
Absent: Abstain: Attested SEP 1 3 1988
Orig. Div. : PW(Constr) Phil Batchelor_
cc: County Administrator Clerk of the Board of
Auditor-Controller Supervisors and County
Design Administrator
PW Accounting
Contractor
BJK:pg By &Jj3gJj
J44,JZ.'_
, DEPUTY
bo: 13 .t9