HomeMy WebLinkAboutMINUTES - 08301988 - 1.9 TO: BOARD OF SUPERVISORS, AS THE GOVERNING BODY OF CONTRA COSTA COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT FROM: J. MICHAEL WALFORD, CHIEF ENGINEER DATE: August 30, 1988 SUBJECT: PROJECT RECOMMENDATION: KELLOGG CREEK - CHANNEL WIDENING PROJECT PROJECT NO. 7522-6D8500-88, BYRON AREA Specific Request(s) or Recommendation(s) & Background & Justification RECOMMENDED ACTION: AUTHORIZE the Chief Engineer to solicit bids pursuant to Section 21191 of the Public Contract Code and enter into a contract to complete the Kellogg Creek - Channel Widening Project, not to exceed $_26, 000. FINANCIAL IMPACT: The project costs, including engineering and appropriate overhead charges, will be funded by Flood Control District Zone 2 . Continued on attachment: X yes Signature: Recommendation of County Administrator Recommendation of Board Committee Approve Other: Si ature s Action of Board Approved as Recommended X v Other Vote of Supervisors I HEREBY CERTIFY THAT THIS IS A TRUE AND CORRECT COPY OF AN ACTION TAKEN AND X Unanimous (Absent3 L Q ENTERED ON THE MINUTES OF Ayes: Noes: THE BOARD OF SUPERVISORS ON Absent: Abstain: DATE SHOWN. Attested August 30 , 1988 Orig. Div. : Public Works (FCE) PHIL BATCHELOR cc: County Administration Clerk of the Board of Auditor-Controller Supervisors and Design County Administrator Accounting Engineering Services Flood Control Engineering DHE:pg/dmw By aJLd1=g . / "y , DEPUTY Kllg.Awd.t9 REASONS FOR RECOMMENDATIONfBACKGROUND: The plans and specifications were approved and the project advertised for bids by the Board of Supervisors on July 19, 1988 . The bid due date was August 18, 1988 and no bids were received. In accordance with Section 22 of the Contra Costa County Flood Control and Water Conservation District Act, . the District can solicit and receive quotes for the .above project. The Flood Control Zone 2 Advisory Board has recommended we proceed with the project on an informal contract basis. DHE:dmw Kllg.Awd.t9