HomeMy WebLinkAboutMINUTES - 08231988 - 1.6 (2) 1-060
TO: Redevelopment Agency
FROM: Phil Batchelor, Executive Director
DATE: August 23, 1988
SUBJECT: Approve Contract Change Order No. 3 for the Pleasant Hill
BART Station Area Landscaping, Project No. 7891-6X5559-85.
SPECIFIC REQUEST(S) OR RECOMMENDATIONS AND BACKGROUND AND- JUSTIFICATION
RECOMMENDATIONS
AUTHORIZE the Chief Engineer to execute Contract Change Order No. 3 to Mori
Hatsushi and Associates, Inc. of Concord, in the amount of $4,851.41, to
provide for changes in the planned work for Pleasant Hill BART Landscaping.
Project No. 7891-6X5559-85.
FISCAL IMPACT
Funds are available from the tax increment and development fees for the
Pleasant Hill BART Specific Plan Area.
CONTINUED ON ATTACHMENT: X YES SIGNATURE: aJ �
RECOMMENDATION OF EXECUTIVE DIRECTOR RECOMIENDATI OF AGEN Y COMMI E
APPROVE OTHER
R6���(AGENCY ON AUG 2.3 ,r 19H8 APPROVED AS RECOMMENDED X OTHER
VOTE OF COMMISSIONERS
X UNANIMOUS (ABSENT 4 ) I HEREBY CERTIFY THAT THIS IS A
AYES: NOES: TRUE AND CORRECT COPY OF AN ACTION
ABSENT: ABSTAIN: TAKEN AND ENTERED ON THE MINUTES
OF THE REDEVELOPMENT AGENCY ON THE
DATE SHOWN.
cc: Redevelopment (Const) ATTESTED August 23 , 1988
Redevelopment Director PHIL BATCHELOR,
Auditor-Controller AGENCY SECRETARY
'Chief Engineer (PW)
BY ,DEPUTY
CONTRA COSTA COUNTY
c-s REVISED(8-85)x-z2 PUBLIC WORKS DEPARTMENT SHEET 1 OF 1
CONTRACT CHANGE ORDER NO. 3 REV.NO. SUPPL.NO.
ROAD NAME W.O.NO. PROJECT NO. DATE
Pleasant Hill BART
Station Area - landscaping 5559 7891-6X5559-85 August 1, 1988
TO:Mori Hatsushi & Associates CONTRACTOR. Chane re uested by Resident Engineer
You are'hereby directed to make the herein described changes from the plans and specifications or do the following described work'not included in the plans and specifications
on this contract.
NOTE:This change order is not effective until approved by the Deputy Public Works Director,Operations and Flood Control.
1. EXTRA WORK AT AGREED PRICES:
A. Restore landscaping at Frumenti Building, Treat. Boulevard and Oak Road ;in
back of sidewalk, to match existing landscaping.
Agreed Price $2,414.29
B. Provide transportation for trees delivered to jobsite.
Agreed Price $1,137.12
2. EXTRA WORK AT FORCE ACCOUNT
Install conduit and wires and hook up area lights at Frumlenti building, Treat
Boulevard and Cherry Lane.
Estimate of Extra Work $1,300.00
labor, equipment and materials approved by the Errjineer as necessary, will be paid for
in accordanoe with the provisions of the contract specifications relating to extra work
at force account.
By signature below, Contractor indicates acceptance of price stated herein as full
compensation for all direct and indirect costs for all work described above, and as
full comlpensatio n for any effects this change may have on the project in its entirety
and/or on the time required to ccuplete the project.
/sa
bla.3.t8
Contractor / Doinstniction Engineer / Resident Engineer / Aroamting - Attn:
ESTIMATED COST: DECREASE$ INCREASE$ 4,851-41_.
BY REASON OF THIS CHANGE 4 WORKING DAYS EXTENSION OF TIME WILL BE ALLOWED.
We,the undersigned contractor,have given careful consideration to the change proposed and hereby agree,if this proposal is approved,that we will provide all equipment,
furnish all materials,except as may otherwise be noted above,and perform all services necessary for the work above specified,and will accept as full payment therefor
the prices shown above.
SUBMITTED: RECOMMENDED:
RESIDENT ENGINEER ASSISTANT PUBLIC WORKS DIRECTOR,
CONSTRUCTION DIV-
ACCEPTED BY CONTRACTOR DATE APPROVED—DEP.PUBLIC WORKSDIR., DATE
OPERATIONS&FLOOD CONT.
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered
work and filing a written protest within the time therein specified.
AUDITOR