HomeMy WebLinkAboutMINUTES - 07261988 - 2.5 _ .. .. _..._ 2 5
BOARD OF SUPERVISORS
TO: It
FROM: Harvey E. Bragdon Contra
Director of Community Development Cma
DATE: February 8, 1988 coily
SUBJECT: Hearing on appeals of the San Ramon Valley Regional Planning
Commission' s approval of Subdivision 6933, in the Diablo area.
SPECIFIC gEQUEST(S) OR RECOMMENDATIONS(S) & BACKGROUND AND JUSTIFICATION
M2UEST
This is a request for two separate appeal of approval of a
tentative map for Subdivision 6933 to divide 106+ acres into five
lots, located northwesterly of the northerly terminus of Alameda
Diablo, in the Diablo area.
1. Appeal of the approval of Subdivision 6933 by Christopher P.
Valle-Riestra on behalf of Save Mount Diablo, the Sierra Club,
the Mount Diablo Audubon Society, the Preserve Ridgeland
Committee and the People for Open Space.
2. Appeal of the Conditions of Approval for Subdivision 6933 by
Sanford M. Skaggs, attorney representing the owner, Robert D.
Stratmore.
RECOMMENDATIONS
1. Deny the appeals concerning the approval of Subdivision 6933
and the Conditions of Approval, by reaffirming the action of
the San Ramon Valley Regional Planning Commission
OR
2. Grant the appeals by denial or modification of Subdiv' sion
6933 and/or the Conditions of Approval.
CONTINUED ON ATTACHMENT: Y " YES SIGNATURE-
BACKGROUND
The Tentative Map Application for Subdivision 6933 was filed March
6, 1987, first scheduled for public hearing June 17, 1987, and
rescheduled several times at the request of the applicant. Staff
had recommended denial mainly because five of the six proposed lots
were at variance to the minimum lot size. Revised plans were
received October 29, 1987, with a reduction of lots and conforming-
lot size. The proposal being consistent with the General Plan and
in compliance with A-20 zoning on the property, was approved
December 16, 1987, with conditions including provisions for further
review to assure that buildings will be visually compatible in the
area and that almost half of the entire site would be placed in a
scenic easement.
ACTION OF BOARD ON . July 26, 1988 APPROVED AS RECOMMENDED OTHER X
The Board of Supervisors on July 12, 1988, closed the public hearing
on the above matter and deferred the matter to today for report from
the Director of Community Development relative to the Williamson Act,
the placement of the building sites and the preclusion of further
subdivision of- the building sites.
The Board having received conditions of approval from the Community
Development Department, Supervisor Schroder commented on the
conditions that addressed the concerns and expressed that he would
like Condition-7,A to read structures shall be sited according to County
Ridgeline Policy to give a little flexibility relative to the
placement of the homes and not require determination today of where
the homes would be sited. Supervisor Schroder moved acceptance of the
recommendation of conditions of approval for Subdivision 6933 .
' rt1
Therefore, IT IS BY THE BOARD ORDERED that Subdivision 6933 is
APPROVED with amended conditions (Exhbit A attached) .
VOTE OF SUPERVISORS
UNANJNp S I HEREBY CERTIFY THAT THIS IS A
OF AN
AYES ly z NOES: 5' , ACTION TAKEN AND ENTEUE AND CORRECT RED ON THE
ABSENT: ABSTAIN: IiIINUTES OF THE BOARD OF
SUPERVISORS ON THE DATE SHOWN.
cc: Community Development Dept. ATTESTED July 26 , 1988
Sanford M. Skaggs PHIL BATCHELOR, CLERK OF
Robert D. Stratmore THE BOARD OF SUPERVISORS
Christopher P. Valle-Riestra, AND COUNTY ADMINISTRATOR
Save Mt. Diablo
Sierra Club
Mt. Diablo Audubon Society
Preserve Area Ridgeland Comm.
People for Open Space BY 14g AJ DEPUTY
Public Works Department
Assessor
CONDITIONS OF APPROVAL FOR SUBDIVISION 6933
1. This approval is based upon the Tentative Map received October 29, 1987.
The Final Map shall not be recorded prior to the termination of the Agri-
cultural Preserve Contract. The contract is presently scheduled to termi-
nate on June 30,. 1992. However, an earlier expiration may occur if the
cancellation petition required under Condition #3 is approved.
2. With the Final Map a scenic easement shall be dedicated to the County for
the entire site. The easement shall generally preclude any buildings from
being erected except as follows:
a two-acre area designated on each lot for a residence and accessory
buildings;
barn, stable or other accessory structure serving an agricultural
function which may be sited elsewhere on the lot with the approval of
the Zoning Administrator.
.The two-acre building site shall be setback from the ridgetop location. .
The precise location of each building site shall be suhject to the final
review .and approval of the Zoning Administrator prior to the filing of a
Final Map. The approved building sites shall be identified on the Final
Map.
C..C. & R's shall identify these_ development restrictions and shall require
that the property owner be responsible for maintaining property outside of
the residential site in natural grasslands, (i .e. , feeding lot prohibited) .
3. Prior to filing a final map, the applicant shall submit. a petition for can-
cellation of the land conservation contract to the Community Development
Department. The petition shall include the required application fee.
4.. Comply with the requirements of the County Health Services Department con-
cerning water supply and sanitary facilities, prior to filing the Final
Map.
5. Prior to recording the final map or issuance of Building Inspection Depart-
ment permits, submit a preliminary engineering geology and soil report
meeting the requirements of Subdivision Ordinance Section 94-4.402, includ-
ing design-level conclusions and recommendations, for review and approval
of the Planning Geologist, allowing 60 days for review. The report shall
be based on subsurface exploration and present recommendations necessary
for long-term stability for structures, .on site sewage fields, roads, `and
erosion control . Cite the above report on the final map and record ac-
knowledgement of the report and these conditions of approval concurrently
with the Final Map.
6. Subdivision grading plans and improvement plans shall ..implement approved
recommendations of the preliminary soil report. '
7. Prior to issuance of a building permit, a site plan shall be subject to the
review and approval of the Zoning Administrator. The. intent of the review
VEIN
. . 1
is to assure that the structures will be -visually compatible with .the sur-
rounding area.
The following design guidelines shall be enforced:
A. Structures shall be sited subject to county ridgeline policy.
B. Residences and any accessory buildings shall be designed as low pro-
file, single-story structures.
C. Structures shall use earthtone colors or other dark hues.
D. Additional landscaping may be required in order to assure adequate
screening of buildings from the valley floor.
8. Comply with drainage, road improvement, traffic and utility requirements as
follows:
A. In accordance with Section 92-2.006 of the County Ordinance Code, this
subdivision shall conform to the provisions of the County Subdivision
Ordinance (Title 9). Any exceptions therefrom must be specifically
listed in this conditional approval statement.
B. The fol-lowing exceptions to Title 9 are permitted for this subdivi-
sion:
1) Chapter 96-10, "Underground Utilities".
2) Section 914-2.006, "Surface Water Flowing from Subdivision", pro-
vided the applicant maintains the existing drainage pattern and
does not dispose concentrated storm waters onto adjacent proper-
ties.
C. Furnish proof to the Public Works Department, Engineering Services
Division, that legal access to the property is available from Diablo
Road.
D. Prevent storm drainage, originating on the property and conveyed in a
concentrated manner, from draining across driveways.
E. Construct a 20-foot paved private roadway to County private road stan
dards, within a 25 foot easement, to serve all parcels in this pro-
posed subdivision. This roadway shall be. extended off-site to Alameda
Diablo.
9. If archaeologic materials are uncovered during grading, trenching or other
on-site excavation, earthwork within 30 meters of these materials shall be
stopped until an archaeologist certified by the Society for California Ar-
chaeology (SCA) and/or the Society of Professional Archaeology (SOPA) has
had an opportunity to evaluate the significance of the find and suggest .
appropriate mitigation measures, if they are deemed necessary.
10. Prior to filing the final map, the applicant shall refer the- project to the
East Bay Regional Park District to provide the District an opportunity to
MEN
Q
3
recommend trail easement connections across the site. Any disagreement
over trail connections shall be decided by the Zoning Administrator.
11. Further °subdivision of the. property shall be prohibited. Any proposed al-
teration in the general configuration of the subdivision shall be referred
to the San Ramon Valley Regional Planning Commission for review and approv-
al .
12. With the filing of this Final Map, the developer shall provide evidence to
the Zoning Administrator from the County Health Services Department and the
San Ramon Valley Fire Protection District that there is adequate water sup-
ply for this development including fire protection.
13. The C.C. & R. 's shall include provision for access and maintenance of fire
protection equipment through the site, and also provision' for a 30 foot
wide fire break adjacent to State Park Lands along this north boundary of
proposed Lot 1.
The following statement is not a condition of approval ; however, the applicant
should be aware of these requirements prior to filing .the Final Subdivision Map
or attempting to secure building permits.
A. Development shall be subject to the ordinance requirements of the San Ramon .
Valley Fire Protection District.
B. Developer promises to cooperate with Diablo Community. Services District for
maintenance and repair of roads within the district.
BT/aa .
11/13/87
11/30/87
12/16/87
7/25/88-df
SUBII/6933C.BT
n n� ' ��