TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: July . 19, 1988
SUBJECT: Property Acquisition, San Pablo Ave. Slide Repair Site 1
Project No. : 0671-6R6733 Task: ACQ Account: 3540
SPECIFIC REQUEST(S) OR RECOMMENDATIONS) & BACKGROUND AND
JUSTIFICATION
I. Recommended Action:
APPROVE Amendment to Right of Way Contract from Jane E.
Ruliffson-Adams and Howard Adams.
AUTHORIZE Public Works Director to execute said Amendment to
Right of Way Contract on behalf of the County.
APPROVE payment of $550. 00 for said property rights and
AUTHORIZE the Auditor-Controller to issue a check in said
amount payable to Jane E. Ruliffson-Adams and Howard Adams to
be forwarded to the Real Property.,.Division for delivery.
Cont'd on Attachment: X yes Signature: �lL�
f Recommendation of County Administrator
Recommendation of Board Committee
Approve Other
Signature(s)
Action of Board on juL 191988
Approved as recommended X Other
Vote of Supervisors ,
X Unanimous (Absent ) I HEREBY CERTIFY THAT THIS
Ayes: ° Noes: IS A TRUE AND CORRECT COPY
Absent: Abstain: _ OF AN ACTION TAKEN AND
ENTERED ON THE MINUTES OF
THE BOARD OF SUPERVISORS ON
DATE SHOWN.
ATTESTED JUL 19 1998
PHIL BATCHELOR, Clerk of
the Board of Supervisors
and County Administrator
BY
DEPUTY
Orig. Div: Public Works (R/P)
cc: County Administrator
Auditor-Controller (via R/P)
P. W. Accounting
Recorder (via R/P)
/3
II. Financial Impact:
Payment of $550. 00 for the: aforementioned contract will come
from San Pablo Avenue slide repair site 1 funds.
III. Reasons for Recommendations:
These property rights are required for the San Pablo Avenue
slide repair site 1 project in accordance with approved plans
and specifications.
V. Consequences of Negative Action:
The project will not have sufficient land rights to allow
construction in accordance with the approved plans and
specifications.
GK:rs