SUBJECT: Contract Award Recommendation:
Drainage Area 13, Lines E & E1 Project
Project No. 7552-6D8460-86, Alamo Area
Specific Requests or Recommendation(s) & Background A justification
RECOMMENDED ACTION:
AWARD the contract for furnishing labor and materials for the subject project to J. Huizar
& Sons, Inc. , the low bidder, in the amount of $159,405.50 and at the unit prices submitted;
and REQUIRE the contractor to present surety bonds for Payment and Faithful Performance in
the amounts of $79,702.75 and $159,405.50, respectively.
DIRECT the Public Works Director to prepare the contract for the project.
AUTHORIZE the Public Works Director to sign the contract on behalf of the Board subject to
the Director having reviewed and found sufficient all required documents, including the
contract signed by the contractor, the aforementioned surety bonds , and a certificate of
insurance.
DIRECT that, in accordance with the project specifications and/or upon the execution of the
contract by the Public Works Director, any bid bonds posted by the bidders be exonerated
and any checks or cash submitted for bid security be returned.
FINANCIAL IMPACT-
The project, including engineering and appropriate overhead charges , is funded by Drainage
Area 13.
REASONS FOR RECOMMENDATION/BACKGROUND:
The plans and specifications were approved and the project advertised for bids by the Board
of Supervisors on July 7, -1987. The bids were received and opened at 255 Glacier Drive,
Martinez, California, on Thursday, July 30, 1987. The construction bids received were as
follows:
1 . J. Huizar & Sons, Inc . $159,405.50
"2. Hess Construction $176,128:50
3. Pfister Excavating $178,600.00
-4-. Golden State Pipeline $215,301 .00
5. Edward J. Pestana $522,165.00
The Engineer's estimated construction cost was $170,000.00.
CONSEQUENCES OF NEGATIVE ACTION:
Continued on attachment: yes Signature: 41 —
_
Recommendation of County Administrator _ Recommendapt4h of Board Committee
Approve Other:
Signature(s):
Action of Board on: AIM 4 1987 Approved as Recommended Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
Unanimous (Absent ) AND ENTERED ON THE MINUTES OF THE
Ayes: Noes: BOARD OF SUPERVISORS ON DATE SHOWN.
Absent: Abstain:
Attested AUG 4 _:.197_
Orig. Div.: Public Works-Construction Phil Batchelor
cc: County Administration Clerk of the Board of
Auditor-Controller Supervisors and County
Design Administ ator
Accounting ,
By y
Deputy Cler
BJK:sa
boi4.t8