HomeMy WebLinkAboutMINUTES - 08251987 - 1.1 TO: BOARD OF SUPERVISORS
FROM: J . MICHAEL WALFORD , PUBLIC WORKS DIRECTOR
DATE: August 25 , 1987
SUBJECT: Approving Plans and Specifications for the North
Richmond Bypass Earthwork , Project No . 0662-6R4178-87 ,
North Richmond Area.
Specific Request ( s ) or Recommendation ( s ) & Background &
Justification
I . RECOMMENDED ACTION :
APPROVE the Plans and Specifications for the North Richmond
Bypass Road Project and ADVERTISE for bids to be received on
Thursday, September 17 , 1987 at 2 :00 p .m.
DIRECT the Clerk of the Board to publish the Notice to
Contractors in accordance with Section 20392 of the Public
Contract Code .
II . FINANCIAL IMPACT:
The estimated contract cost of the project is $632 ,000 . Funding
for the contract cost , contingencies , inspection , etc . will be
shared with the City of Richmond . The County will be responsible
for acquiring additional right of way in the County portion of
the project .
III . REASONS FOR RECOMMENDATION/BACKGROUND:
The Public Works Director has filed with the Board of Supervisors
the Plans and Specifications for the North Richmond Bypass
Earthwork Project .
An Environmental Impact Report for the North Richmond Bypass Road
Project was prepared and certified by the City of Richmond . A
Notice of Determination by the City of Richmond has been filed
with the County Clerk .
Continued on attachment: X yes Signa
Recommendation of County Administr for
Recommendation of Board Committee
Approve Other:
Signature(s) :
Action of Board on: AUG 25 1987
Approved as Recommended_ Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS
A TRUE AND CORRECT COPY OF AN
X_ Unanimous (AbsentLT= ) ACTION TAKEN AND ENTERED ON
Ayes : Noes : THE MINUTES OF THE BOARD OF
Absent: Abstain : SUPERVISORS ON DATE SHOWN.
Attested AUG 25 1987
Orig. Div . : PW (Design ) Phil Batchelor,
cc : County Administrator Clerk of the Board
Auditor- Controller of Supervisors and
PW Accounting County -Administrator
Construction
Community Development
Attn : Gus Almquist
City of Richmond
JC/bb Byr..s '
\ bo :25 .t8 Deputy Clerk
This project will construct drainage improvements and place earth
fill on portions of Phases 2 and 3 of the North Richmond Bypass
( proposed State Route 93) road project . ''Bridges for the Bypass
are now under construction over Wildcat Creek and San Pablo
Creek .
The general prevailing rates of wages , which shall be the minimum
rates paid on this project , have been filed with the Clerk of the
Board and copies will be made available to any interested party
upon request .