TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: July 21 , 1987
SUBJECT: EAST/CENTRAL COUNTY TRAVEL CORRIDOR AREA OF BENEFIT
Specific Requests ) or Recommendation ( s ) & Background &
Justification
I . RECOMMENDATION
1 . Fix August 18 , 1987 at 10 : 30 a .m. as the date and time for a
public hearing for the adoption of an ordinance amending the
fee schedule and adoption of an urgency ordinance allowing
the amended fee to be collected immediately for the
East/Central County Travel Corridor Area of Benefit .
2 . Direct the Public Works Director to give notice of the
hearing in accordance with Government Code Sections 65091 ,
65962 and 66484 .
3 . Direct the Public Works Director to file a copy of the
Amendment to the Development Program Report for the
East/Central County Travel Corridor Area of Benefit with the
Clerk of the Board.
II . FINANCIAL IMPACT
None.
III . REASONS FOR RECOMMENDATION/BACKGROUND
The Board of Supervisors adopted the East/Central County Travel
Corridor Area of Benefit September 16 , 1986 for the purpose of
funding an additional lane in the westbound direction of Highway
4 from Willow Pass Road in West Pittsburg to Willow Pass Road in
Concord . The additional lane is needed so that traffic
congestion along this segment over the next five years will not
significantly exceed the 1986 level of congestion . This is
considered a temporarysolution until this segment of the travel
corridor can be improved to the ultimate ( 20 year) design.
Continued on attachment: X yes Signature :
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other :
Signature(s) :
Action of Board on : JUL 21 i987
Approved as Recommended Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS
A TRUE AND CORRECT COPY OF AN
X _ Unanimous (Absent ) ACTION TAKEN AND ENTERED ON
Ayes : Noes : THE MINUTES OF THE BOARD OF
Absent : Abstain : SUPERVISORS ON DATE SHOWN.
Attested JUL 21 1981
Orig . Div . : Public Works ( RE) PHIL BATCHELOR,
Ot Supervisor Torlakson OF SUPERVISORS AND
Comm. Dev. COUNTY ADMINISTRATOR
JRB :lf
BO: 21 . t7
BY
DEPUTY CLERK
ti
Board of Supervisors
July 21 , 1987
Page Two
On September 30 , 1986 , the Board approved a Consulting Services
Agreement to prepare the construction plans for the project . The
County and the cities of Antioch , Brentwood and Pittsburg
executed a separate agreement to share the cost of these plans.
The County ' s maximum obligation was $26 ,000 .
The construction plans are complete and the project will be ready
for advertising for bids this fall . At that time Caltrans will
request the funds from the local agencies to pay for the
construction.
Because of revisions to the cost of the project it is necessary
to raise the Area of Benefit fee to insure the County will be
able to pay its share.
IV. CONSEQUENCES OF NEGATIVE ACTION
Negative action may result in the County not being able to pay
its share and the project being postponed