HomeMy WebLinkAboutMINUTES - 08281984 - X.5 THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on August 28, 1984 by the following vote:
AYES: Supervisors Powers ,'Janden, Schroder, McPeak, Torlakson
NOES: None
ABSENT: None
ABSTAIN: None
SUBJECT: In the Matter of Approving Plans and Specifications and Awarding
Contract for Recreation Area Overlay at Byron Boys Ranch, Project No.
4413-4172; W.O. 5578, Byron Area.
Bidder Total Amount
Teichert Construction $8,200.00
P. 0. Box 1118
Stockton, California 95201
B and B Grading and Paving, Inc.
WHEREAS Plans and Specifications for Recreation Area Overlay at
Byron Boys Ranch have been filed with the Board this day by the Public
Works Director, and informal bids being duly invited and received by
the Public Works Director; and
WHEREAS the general prevailing rates of wages, which shall be the
minimum rates paid on this project, have been approved by this Board;
and
WHEREAS this project is considered exempt from Environmental Impact
Report guidelines as a CEQA Class 1C Categorical Exemption under County
Guidelines, the Board hereby concurs in this determination and directs
the Public Works Director to file a Notice of Exemption with the County
Clerk;
IT IS BY THE BOARD ORDERED that said Plans and Specifications are
hereby APPROVED.
The Public Works Director recommending that the bid listed first
above is the lowest responsible bid and this Board concurring and so ,,
finding;
IT IS FURTHER ORDERED that the contract for the furnishing of labor
and materials for said work is awarded to said first listed bidder at
the listed amount and at the unit prices submitted in said bid; and that
the Public Works Department shall prepare the contract therefor.
IT IS FURTHER ORDERED that, after the contractor has signed the
contract and returned it with any required certificates of insurance,
and the County Counsel has reviewed and approved them as to form, the
Public Works Director is authorized to sign the contract.
I tweby o*MfY"thIs It a true and correct copy Of
on action taken and entered on the rn;nutes of the
Orig.Dept.: Public Works Department Board of Supervisors 0-1 the date shown.
Design and Construction Division ATTESTED: '-_Z
cc: County Administrator J.R. OLSSON, COUNTY CLERK
County Auditor-Controller and ex officio Clerk of the Board
Public Works Director
Design and Construction Division
Accounting Division
BY ,Deputy
Land Development Division
Contractor (via P/wj
DC:BYRONBO.T8 004311