HomeMy WebLinkAboutRESOLUTIONS - 01272003 - 99-274 Recording Requested By:
Contra Costa County Public Works Dept.
Construction Division
255 Glacier Drive
Martinez, CA 94553
Return to:
WHEN RECORDED, RETURN TO CLERK
BOARD OF SUPERVISORS
BOARD OF SUPERVISORS, CONTRA COSTA COUNTY, CALIFORNIA
In the Matter of Accepting and Giving } RESOLUTION OF ACCEPTANCE
Notice of Completion of Contract for ) and NOTICE OF COMPLETION
Marsh Creek Levee Repair ) (C.C. § 3086, 3093)
Project No.7521-091-79-97) RESOLUTION NO. 991274
The Board of Supervisors of Contra Costa County RESOLVES that:
The County of Contra Costa on July 29, 1998 contracted with Gordon N. Ball, Inc., to excavate and
replace rock slope protection and place a horizontal layer of rock for drainage, with United States Fidelity
and Guaranty Company as surety, for work to be performed on the grounds of the County; and
The Public Works Director reports that said work has been inspected and complies with the approved
plans, special provisions and standard specifications and recommends its acceptance as complete as
of April 28, 1999.
Therefore, said work is ACCEPTED as completed on said date, and the Clerk shall file with the County
Recorder a copy of this Resolution and Notice as a Notice of Completion for said contract.
PASSED BY THE BOARD on May 25, 1999 by the following vote:
AYES: Supervisors Gioia, Uilkema, Gerber, DeSaulnier and Canciamilla
NOES: None
ABS NT' None
CERTIFICATION AND VERIFICATION
I hereby certify that this is a true and correct copy of an
action taken and entered on the minutes of the Board of
Contact: Mike Carlson (925)313-2321 Supervisors on the date shown.
Orig. Dept.:Public Works(Const.)
cc: Record and Return
Auditor ATTESTED: Msy 25, 11999
Public Works- Accounting PHIL BATCHELOR, Clerk of the Board of Supervisors and
- Construction, R.Bruno County Administr or
- Traffic,S.Kersevan
Contractor
RBlkj By
� ,
G:\GrpData\Const\BO\1999\05-May\MCLR-25.doc Deputy
RESOLUTION NO. ( 274