HomeMy WebLinkAboutRESOLUTIONS - 01031967 - 1967-002 IN THE BOARD OF SUPERVISORS
CF
CONTRA COSTA COUNTY, STATE OF CALIFORNIA
In the Matter of. Accepting and Giving Notice )
of Completion of Contract with Robert R. } RESOLUTIION OF ACCEPTANCE
Murdoch dba Murdoch Engineering & Construc- } and NOTICE OF COMPLETION
tion Co., for construction of the Concord }
Boulevard Bridge over Mt. Diablo Creek, } RESOLUTION No. 67/2
Concord Area. Project No. 4671--4:1.€4-66. �
WHEW,AS3, the County of Contra Costa on July 26, 1966, contracted with
Robert R. Murdoch. dba Murdoch Engineering & Construction Co., 100 Ivy .give,,
Orinda,, California, for construction of a second span of Concord. Boulevard Bridge
over Mt. Diablo Creek, Concord area,, with United Pacific insurance Company as
surety for said contractor, for work to be performed on the grounds of the county
on Concord Boulevard, Concord area; and
akS, the Public Works Director recon ends acceptance of said work,
which has been inspected and complies with the approved plans, special provisions,
and standard specifications., and said contractor completed said work on December 20,
1966;
IT IS R.FSOL�,� that said. work is accepted as completed on said date,, and
the Clerk shall ;pile with the County Recorder a copy of this Resolution and Notice
as a Notice of Completion for said contract.
IT IS _'+UR VER RESOLVED that a twenty-five (25) day extension of contract
time be granted due to delays resulting from a utility relocation (3 days), ars ex-
tension
xtension of wingwalls (2 .days), striping of the roadway (1 day), and a bridge rail-
ing delivery delay of 19 dabs.
PASMD AND ADOPTM this 3rd day of January-, 1967, by the following vote
of the Hoard.
Ate: Supervisors Fames P. Kenny, James E. Moriarty, Thomas John Coll,
Edmund A. Linscheid.
NOES: None.
ABSENT: Supervisor Alfred M. Dias.
RESOLUTION NO. 67/2
yyzR
z